Implementation methodology

How we implement Sage Intacct

Every implementation we lead follows five phases: Define, Build, Migrate, Test and Launch, followed by about six weeks of hypercare through your first close. The constants are transparency, collaboration and a system built around how your business actually operates.

The timeline

Sequential in concept, overlapping in practice

The phases run in order, but they overlap. Migration, for example, runs through nearly the whole project. Here's how a typical project lays out.

DefineWeeks 1–3
1–3
BuildWeeks 3–11
3–11
MigrateAlongside, weeks 2–15
2–15
TestWorking model ~week 8, then UAT and training
11–14
LaunchWeeks 15–16
15–16
HypercareAbout 6 weeks after go-live
17–22
Week 1Week 6Week 11Week 16 · go-liveWeek 22
Phase by phase

What happens, what you get, what we need from you

Open any phase for the detail.

1

Define

About 3 weeks

Workshops on how you work today, then requirements and future-state process maps.

What happens

  • Kickoff and a project plan built from our template, tailored to you
  • Business process review workshops on each current process
  • Requirements drafted by us, refined with you
  • Future-state process flows in Sage Intacct

What you get

  • A project plan that fits your business
  • A signed-off list of system requirements
  • Future-state process diagrams
  • A data migration roadmap

What we need from you

  • Your project team, key stakeholders and subject matter experts for a few days of workshops
  • Time to review and approve the requirements
Read the detail

It all starts with a plan

We start with a template we've refined over years of repetition, then customize it for every project. There's no need to reinvent the wheel each time, but no two businesses are the same, so their needs, constraints and preferences vary. That's why we put real effort into a plan for each implementation that actually makes sense.

Business process review workshops

With some basic discovery done and a high-level plan in place, it's time to get our hands dirty. Ideally, we get the whole project team, key stakeholders, subject matter experts and the office dog together for a few days in front of a whiteboard. We walk through each step of your current processes as a jumping-off point for imagining the new world, and begin drafting the processes and system requirements that support that future state.

Requirements

The workshops produce a discrete list of system requirements. We draft them first, then refine them with you until every detail specific to your organization is nailed down. This list, together with the data migration tasks, becomes the foundation for everything we track toward go-live.

Future-state processes

With a solid understanding of your current processes, pain points and needs, we redesign the future state in Sage Intacct. We document it as process flow diagrams. They frame testing, give users a quick reference after go-live and ground the discussion as requirements are finalized.

2

Build

About 8 weeks

Configure Sage Intacct in short cycles, with your team reviewing as we go.

What happens

  • Chart of accounts, dimensions, workflows, approvals, security roles, reports and dashboards
  • One module at a time: configure, check against requirements, adjust
  • Integrations with banks, payroll, CRM or e-commerce built and tested

What you get

  • Regular check-ins with visible progress
  • A system that's functionally complete and ready to test
  • Working, tested integrations

What we need from you

  • A regular check-in to review progress
  • Quick decisions on open design questions
  • Contacts and access for the systems we connect
Read the detail

The Build phase is iterative by design. We don't disappear into a cave for three months and emerge with a finished product. We work in cycles: configure a module, check it against your requirements, adjust based on what we learn, and move on to the next. Your project team stays involved throughout, reviewing progress in regular check-ins, so there are no surprises later.

For projects that include integrations with other systems, such as banks, payroll providers, CRMs or e-commerce platforms, this is also where we build and test those connections. The goal by the end of Build is a system that's functionally complete and ready for your team to put through its paces.

3

Migrate

Runs alongside, weeks 2–15

Core records, summarized history and open transactions, mapped and reconciled.

What happens

  • We agree what comes over from your old system and how it maps
  • Core records, then 1–2 years of summarized GL history, then open transactions
  • Source data tied to control totals before import, and checked again after

What you get

  • Documented mapping decisions
  • Year-over-year reporting from day one
  • Open bills, orders and checks that carry on cleanly
  • An opening position that reconciles

What we need from you

  • Clean-up of master records before import: duplicates, required fields, names and IDs
  • Exports and approved control totals from your old system
  • The people who own the data to check it after each load
Read the detail

Your data, your rules

The best accounting system in the world is worthless without the data you rely on. In Migrate, we work out together exactly what needs to come over from your old system and how it maps into Sage Intacct. We treat it as its own phase because the work is distinct, but on the timeline it spans most of the project. It breaks down into three kinds of data. For the full approach, read our guide to Sage Intacct data migration.

Core data

Chart of accounts, legal entities, locations, bank accounts, departments, classes, customers, vendors, employees, projects, tasks, items, contracts and on. Once upon a time we'd say Sage Intacct has eight standard dimensions, or ways to break your chart of accounts into multiple fields. Today it's closer to 12, depending on your modules, and by the time you read this it could be 20 or more, not counting the custom dimensions you can add.

Historic data

Historic data is the transaction history from your old system: what you need in Sage Intacct to run year-over-year comparisons, close-period reporting and trend analysis without logging back into the old system every time someone asks "what did last year look like?" We usually recommend bringing over 1–2 years of GL history, summarized by month, legal entity, GL account and any other dimensions critical to your reporting. That's enough for continuity and context without dragging along every transaction since the dawn of time.

Cutover data

Sometimes called "open data," these are transactions in multi-step workflows that started in your old system and won't be finished before go-live. Examples include bills entered but not yet paid, customer orders not yet fulfilled and outstanding checks for bank reconciliation.

4

Test

Working model mid-Build, then about 4 weeks

A working-model session at the halfway mark, then hands-on testing and role-based training.

What happens

  • A working-model session around the halfway mark
  • Our own end-to-end testing
  • User acceptance testing (UAT): we walk you through, then your team tries to break it
  • Role-based training for everyone who'll use the system

What you get

  • Gaps found while changes are still cheap
  • An issue log worked to closure
  • Users who know where to click on go-live morning

What we need from you

  • The people who'll use the system doing their real work in testing, ideally several days together on site
  • Everyone who'll use the system at their training session
Read the detail

Working models

Sometimes called a conference room pilot, a working model is a structured walkthrough of your new system while it's still being built, typically around the halfway mark. We sit down with your team and run core business processes end to end in a partly configured environment. The goal isn't perfection; it's early feedback. Are the workflows intuitive? Did we miss a step? Does the approval routing reflect how your team really works? We often run smaller versions throughout the project, but a dedicated session to surface gaps before formal testing lets us course-correct while changes are still cheap and easy.

Iterative user acceptance testing

By now our team has tested extensively. First we lead your team through key business processes in the new system, end to end. Then we turn your team loose with one goal: break it. Find the exceptions, the missed requirements, the cases no one remembered to bring up.

We'll never know your business as well as you do, and it would be naive to assume otherwise. We want the people who'll use the system every day to try to do their actual work in it. That gets as close to reality as possible while you still have the safety of a test environment and our team beside you. Ideally these sessions run on site for several days, with the whole project team together in one room.

End-user training

By this point your project team has been living and breathing the new system for months, but the rest of your organization hasn't. End-user training bridges that gap. We build role-based sessions around how each group will actually use Sage Intacct: AP clerks get hands-on with bill entry and payment runs, project managers walk through time and expense workflows, and controllers see reporting and the close from start to finish. The emphasis is day-one readiness: not a feature tour, but the confidence to sit down on go-live morning and know exactly where to click.

5

Launch

About 2 weeks

A coordinated cutover: final checks, communication and timing across teams.

What happens

  • Final configuration, integration checks, roles and permissions
  • A detailed go-live checklist
  • Communication to leadership, departments, vendors and users
  • Timing for the old system's cutoff, bank feeds and open transactions

What you get

  • A go-live everyone saw coming
  • Open items handed over cleanly
  • A fallback plan for processes that can't stop

What we need from you

  • A go or no-go decision
  • A cutoff date for entries in the old system
  • Help sending the communications
Read the detail

Go-live doesn't just happen; it's orchestrated. Launch is a coordinated cutover that brings together every technical and organizational thread we've been pulling on throughout the project. On the technical side, we finalize configuration, double-check integrations, confirm user roles and permissions, and work through a detailed go-live checklist so nothing slips through the cracks. On the people side, we help you manage communication: telling leadership, department heads, vendors and users what's changing, when, and what to expect on day one. We coordinate timing across teams so the old system's cutoff, bank feed transitions and open-transaction handoffs all land cleanly. Think of it as mission control for your go-live.

+

Hypercare

About 6 weeks after go-live

Hands-on support through your first month-end close.

What happens

  • We're on call as your team processes real transactions
  • Questions answered, edge cases fixed, workflows fine-tuned
  • Your first month-end close, done together

What you get

  • A clean first close
  • A list of open items and future improvements
  • A team that owns the system

What we need from you

  • Tell us about issues as they come up
  • Run the first close with us
Read the detail

The system is live. Now what? Hypercare is the intensive, hands-on support window after go-live, usually about six weeks through your first month-end close in the new system. Our team is on call and actively engaged as your users work through real transactions for the first time: answering questions, troubleshooting edge cases, fine-tuning workflows and fixing anything that only shows up once the system meets the full weight of daily operations.

The goal is a clean first close, and the peace of mind of knowing you're not doing it alone. By the end of hypercare, your team isn't just using Sage Intacct; they own it.

Risks

What can go wrong, and how we prevent it

Implementations have a reputation for a reason. These are the problems we see most, and what each phase does about them.

The risk

Moving messy data into a clean system

Duplicate vendors, three naming conventions, account codes nobody can explain.

What it costs

An import doesn't fix any of it. It moves the problem, quickly and efficiently, into a newer, more expensive system, where the built-in business logic starts throwing errors.

How we prevent it

Clean master records before anything moves: merge duplicates, fill required fields, standardize names and IDs. Master data comes before history.

Migrate
The risk

Finding out the old system was out of balance

Discovering it during go-live week, after the data has moved.

What it costs

Every variance becomes a guessing game between three suspects: the source data, the mapping and the import.

How we prevent it

Tie the source to approved control totals first: trial balance by period and entity, AP and AR agings, bank balances. Then lock them for the migration.

Migrate
The risk

Trusting "import successful"

A green message means Sage Intacct accepted the file, not that the result is right.

What it costs

An order line with no unit price falls back to the item's base price: about $124 a case instead of $4.41. The import succeeded; the number was nonsense.

How we prevent it

Compare record counts, control totals and key balances after every load. Data owners check their own records, and key reports are run for migrated periods before go-live.

MigrateTest
The risk

Workflow gaps found too late

A missed step or wrong approval route that nobody sees until testing, or until go-live.

What it costs

Late changes are expensive and squeeze the timeline when there's least room.

How we prevent it

A working-model session at the halfway mark, running real processes end to end while changes are still cheap.

Test
The risk

Users who aren't ready on day one

The project team knows the system; the rest of the company doesn't.

What it costs

Slow work, workarounds and a flood of questions during the first close.

How we prevent it

Role-based training around each group's real work: AP clerks run payments, project managers enter time and expenses, controllers walk the close.

Test
The risk

A critical process stalls at cutover

Payroll, billing on the first of the month or cash application can't wait for a fix.

What it costs

People don't get paid and customers don't get billed. Running both systems side by side indefinitely isn't the answer either: it doubles the work without doubling the staff.

How we prevent it

Read-only access to the old system for history, and a documented fallback for critical processes during the first few cycles. Then hypercare through the first close.

LaunchHypercare
Common questions

What finance leaders ask us

How long does an implementation take?

A typical project runs about 16 weeks from kickoff to go-live, then about six weeks of hypercare through your first close. More entities, modules, integrations or history add time; a single entity with clean data can go faster. We'll give you a real estimate once we've scoped your project.

How much of our team's time will it take?

Plan on a project lead for a few hours a week throughout. Subject matter experts join for a few days of workshops in Define and several days of testing in Test, and everyone who'll use the system attends role-based training. Data clean-up is the part teams underestimate, so start it early.

Can we keep our old system?

Yes, and we recommend keeping read-only access for as long as you need to retain records. Someone will eventually need an original invoice or an old report. For the first few cycles we also plan a fallback for processes that can't stop, like payroll and billing. What we don't recommend is running both systems in parallel indefinitely.

We're partway through an implementation with another partner. Can you take over?

Yes. We start with a short review of where things stand: requirements, configuration, data and open issues. Then we pick up in whichever phase you're in and tell you plainly what needs redoing and what doesn't.